THE PROJECT

The development consisted of a newly constructed 325,000 square foot distribution facility and represented a new investment of approximately $14 million for site preparation activities, site development and vertical construction.

OUR ROLE

AKT Peerless utilized our extensive background in construction and cumulative cost data to perform a preliminary review of the project prior to loan closing. The initial review helped pinpoint any major factors that could potentially impact the original proposed budget or schedule throughout the duration of the project.

AKT Peerless’ review of the monthly pay application and site inspections provided regular insight into any design or scheduling changes to the project. The information at the meetings was regularly communicated to CIBC so they could manage any financial risks throughout the various stages of construction.

THE RESULTS

AKT Peerless’ comprehensive monitoring services provides CIBC Bank: Protection from liability exposure during the initial review of the construction documents. Recommendations for budgetary contingencies to account for unforeseen conditions. Recurring updates on any potential risks or modifications to the construction design throughout the construction. Assurance that the monthly disbursements of loan funds were not premature but were consistent with the appropriate project milestones.

Our Other Projects

Former Middle Grounds Landfill, Bay City, MI

Fire Station, Bay City, MI

HUD Environmental Assessments, Akron, OH

Surrey Square Shopping Mall, Norwood, OH

Due Diligence and Risk Reduction Program for K. Hovnanian Homes Real Estate

Preacquisition Due Diligence, Cincinnati, OH

Construction Loan Monitoring for Queen City Textile Building, Cincinnati, OH

Construction Loan Monitoring for MAGNET Headquarters, Cleveland, OH

Archdiocese of Detroit (AoD) AHERA School Management

Gasoline Station and Convenience Store, Toulon, IL

Salt Shed, Chicago, IL

AKT Peerless New Development Downers Grove IL

New Development, Downers Grove, IL

Vacant Lot turned New Development, Mount Prospect, IL

Riverfront Campus Redevelopment, Saginaw, MI

North Peak Brewery, Bay City, MI

U.S. Post Office ACM Abatement Management, Bellevue, MI

Saginaw Public Schools, Saginaw, MI

The Albion at Oak Park, Oak Park, IL​

Navy Pier, Chicago, IL

Hotel Clermont, Atlanta, GA

Founder’s Landing, Marquette, MI

Fordson Island, Dearborn, MI

Guardian Industries

Guardian Industries, Michigan Locations

Energy Utility, Jackson, MI

Powerhouse and Paper Mill, Monroe, MI

Distribution Warehouse, Indianapolis, IN

Springs at Greenville, Greenville, SC

Compliance Solution for EECBG Program, Cook County, IL

Commercial Area, Ionia, MI

Henry Ford Cancer Care Center, Detroit, MI

Hotel St. Regis, Detroit, MI

Former La-Z-Boy Manufacturing Facility, Monroe, MI

Former Marysville Power Station, Marysville, MI

Grandview Commons, Dexter, MI

Mosaic Eastern Market Redevelopment Project, Detroit, MI

Former Summit Place Mall Redevelopment Project, Waterford Township, MI

Lafayette West, Detroit, MI

The Cambria @ The Ashton, Detroit, MI

The Exchange Development, Kalamazoo, MI

Sharon Steel, Dearborn, MI

Cardinal Health, Detroit, MI

McCormick Place, Chicago, IL

Fueling Station, Tifton, GA

Tao Restaurant, Chicago, IL

Fueling Station, Thomson, GA

Residential Condominium Development, Chicago, IL

Filling Station Redevelopment, Hampshire, IL

Sparta Foundry Area, Sparta, MI