Industrial Facility, MI

Soil vapor extraction (SVE) and in situ chemical oxidation (ISCO) for treatment of chlorinated solvents.

THE PROJECT

AKT Peerless provided environmental remediation services for an industrial facility that experienced a release of chlorinated solvents. The scope of work included a feasibility analysis of four proposed remediation options. Soil vapor extraction (SVE) in combination with in situ chemical oxidation (ISCO) was chosen as the remediation option. Pilot-scale testing to evaluate the feasibility and determine optimal full-scale design parameters was completed before system installation.  A full-scale SVE system was designed to treat approximately 240,000 cubic feet of soil.  The system included four independently controlled treatment zones with multiple manifolds that can work independently of each other, in some combination with others, or all at once. This control will allow treatment to be focused on one specific area of the plume as necessary or to be applied across the entire plume at once, as dictated by pressure readings, sampling results, soil, and/or groundwater conditions. 

ISCO using permanganate injection (the second of two remediation technologies for this facility) is a very effective groundwater remediation technology for the treatment of common chlorinated solvents such as tetrachloroethylene (PCE) and trichloroethylene (TCE). The key benefit of ISCO technology is that it provides significantly enhanced destruction of target contaminants (complete mineralization to carbon dioxide and water is the desired endpoint of an ISCO process) within a relatively short period of time (i.e., months) by comparison with standard pump & treat approaches that require years or even decades to restore groundwater quality. A key benefit of the ISCO approach is that it can accelerate the dissolution of dense non-aqueous phase liquids (DNAPLs) by order(s) of magnitude, which is expected to reduce the time and cost for source remediation by a comparable factor.

Once the contaminant concentration in the extracted soil vapor declines to a near steady-state, chemical injection will be used to treat the groundwater beneath the source area. The goal of this process is to reduce the mass of contamination in the source area, control leaching from the source area, and allow the downgradient groundwater plume to diminish over time. 

OUR ROLE

AKT Peerless’ Feasibility Study and Pilot Tests ensured effective remediation technologies were selected for addressing the chlorinated solvents issues.  Following the Pilot Tests, AKT Peerless designed the remediation systems, completed construction oversight and currently conducts operations and maintenance.       

AKT Peerless’ maintenance activities for this project include performing routine site and equipment inspections, sampling activities, and reporting documentation. Sampling events to monitor the effectiveness of the SVE systems are required and used to evaluate the concentration of contaminants extracted and the useful remaining life of the carbon columns in order to facilitate carbon change out.

THE RESULTS

AKT Peerless completed a feasibility analysis, pilot tests, design of the remediation systems, construction oversight and currently conducts operations and maintenance.  The SVE systems are expected to operate for 2-4 years for the SVE system. Quarterly groundwater monitoring will continue to be conducted during SVE system operations and for a period of time after (to be coordinated with EGLE). ISCO Injection (two applications) will take place once soil vapor concentrations decline to a relatively steady state.

Our Other Projects

Former Middle Grounds Landfill, Bay City, MI

Fire Station, Bay City, MI

HUD Environmental Assessments, Akron, OH

Surrey Square Shopping Mall, Norwood, OH

Due Diligence and Risk Reduction Program for K. Hovnanian Homes Real Estate

Preacquisition Due Diligence, Cincinnati, OH

Construction Loan Monitoring for Queen City Textile Building, Cincinnati, OH

Construction Loan Monitoring for MAGNET Headquarters, Cleveland, OH

Archdiocese of Detroit (AoD) AHERA School Management

Gasoline Station and Convenience Store, Toulon, IL

Salt Shed, Chicago, IL

AKT Peerless New Development Downers Grove IL

New Development, Downers Grove, IL

Vacant Lot turned New Development, Mount Prospect, IL

Riverfront Campus Redevelopment, Saginaw, MI

North Peak Brewery, Bay City, MI

U.S. Post Office ACM Abatement Management, Bellevue, MI

Saginaw Public Schools, Saginaw, MI

The Albion at Oak Park, Oak Park, IL​

Navy Pier, Chicago, IL

Hotel Clermont, Atlanta, GA

Founder’s Landing, Marquette, MI

Fordson Island, Dearborn, MI

Guardian Industries

Guardian Industries, Michigan Locations

Energy Utility, Jackson, MI

Powerhouse and Paper Mill, Monroe, MI

Distribution Warehouse, Indianapolis, IN

Springs at Greenville, Greenville, SC

Compliance Solution for EECBG Program, Cook County, IL

Commercial Area, Ionia, MI

Henry Ford Cancer Care Center, Detroit, MI

Hotel St. Regis, Detroit, MI

Former La-Z-Boy Manufacturing Facility, Monroe, MI

Former Marysville Power Station, Marysville, MI

Grandview Commons, Dexter, MI

Mosaic Eastern Market Redevelopment Project, Detroit, MI

Former Summit Place Mall Redevelopment Project, Waterford Township, MI

Lafayette West, Detroit, MI

The Cambria @ The Ashton, Detroit, MI

The Exchange Development, Kalamazoo, MI

Sharon Steel, Dearborn, MI

Cardinal Health, Detroit, MI

McCormick Place, Chicago, IL

Fueling Station, Tifton, GA

Industrial Warehouse, Huntersville, NC

Tao Restaurant, Chicago, IL

Fueling Station, Thomson, GA

Residential Condominium Development, Chicago, IL

Filling Station Redevelopment, Hampshire, IL